Project Start Date: Fri 10/6/00
Project Finish Date: Tue 10/31/00
This Project Update was done on 09/01/2004 06:35 PM
| Task ID | Name | Percent Complete | Start Date | Duration | Actual Work | Duration Variance | Finish Date |
Resource | Scheduled Work | Work Variance |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Training Room Prep | 100% | Fri 10/6/00 | 0.50 days | 2 hrs | -.3 days | Fri 10/6 |
DCAA | 6 hrs | -34 hrs |
| 5 | Power Modifications | 100% | Mon 10/9/00 | 4.0 days | 51 hrs | 1.0 day | Thu 10/12 | Double Eagle | 51 hrs | -69 hrs |
| 22 | Network Connections | 100% | Mon 10/9/00 | 2.0 days | 31 hrs | 2.0 days | Tue 10/10 | SMED | 31 hrs | 31 hrs |
| 28 | Patch Panel Installation | 100% | Tue 10/10/00 | 4.0 days | 25 hrs | 4.0 days | Fri 10/13 | SMED | 25 hrs | 25 hrs |
| 34 | Testing & Evaluation | 100% | Wed 10/11/00 | 1.1 days | 4 hrs | 1.1 days | Thu 10/12 | Simplex | 8 hrs | 8 hrs |
|
|
|
Resource | Over- Allocated | Scheduled Work |
|---|---|---|
| DCAA | Yes | 18 hrs |
| Double Eagle | Yes | 33 hrs |
| SMED (BI) | Yes | 47 hrs |
| Simplex (PC) | Yes | 64 hrs |