Project Start Date: Fri October 06
Project Finish Date: Tue October 31
This Project was updated on:
09/01/2004 06:35 PM.
PM Home || Project Summary || Current Project Status || Resources || Photos || PM Sample Site
| Dates |
| Start | Fri 10/06 | Finish | Tue 10/31 | |
| Baseline Start | Mon 10/02 | Baseline Finish | Fri 10/13 | |
| Actual Start | Fri 10/06 | Actual Finish | Tue 10/31 | |
| Start Variance | 4 days | Finish Variance | 18 days |
| Duration |
| Scheduled | 18 days | Remaining | 0 days | |
| Baseline | 5 days | Actual | 18 days | |
| Variance | 13 days | % Complete | 100% |
| Work |
| Scheduled | 162 hrs | Remaining | 0 days | |
| Baseline | 168 hrs | Actual | 162 days | |
| Variance | -6 hrs | % Complete | 100% |
| Cost |
| Scheduled | $0.00 | Remaining | $0.00 | |
| Baseline | $0.00 | Actual | $0.00 | |
| Variance | $0.00 |
| Task Status |
| Not Started | 0 |
| In Progress | 0 |
| Completed | 45 |
| Total Task | 45 |
| Resource Status |
| Resources | 0 |
| Over Allocated Resources | 4 |
| Total Resources | 4 |
PM Home || Project Summary || Current Project Status || Resource || Top || PM Sample Site
| Task ID | Task Name | Start Date | Finish Date | Percent Complete |
|---|---|---|---|---|
| 1 | Training Room Prep | Fri 10/6 | Fri 10/6 | 100% |
| 5 | Power Modifications | Mon 10/9 | Thu 10/12 | 100% |
| 22 | Network Connections | Mon 10/9 | Tue 10/10 | 100% |
| 28 | Patch Panel Installation | Tue 10/10 | Fri 10/13 | 100% |
| 34 | Testing & Evaluation | Wed 10/11 | Thu 10/12 | 100% |
| 45 | Provide
as-built Dwgs
| Tue 10/31 | Tue 10/31 | 100% |
PM Home
|| Project
Summary || Current Project Status || Resource
|| Top || Photos
|| PM
Sample Site
| Resource Name | Scheduled Work | % Work Complete | Actual Work | Overtime Work | Start Date | Finish Date | Project Length | Over Allocated | Peak Allocation |
|---|---|---|---|---|---|---|---|---|---|
| DCAA | 18 hrs | 100% | 18 hrs | 0 hrs | Fri 10/6 | Thu 10/12 | 40 hrs | Yes | 400% |
| Double Eagle | 33 hrs | 100% | 33 hrs | 0 hrs | Mon 10/9 | Fri 10/13 | 40 hrs | Yes | 150% |
| SMED (BI) | 47 hrs | 100% | 47 hrs | 0 hrs | Mon 10/9 | Fri 10/13 | 40 hrs | Yes | 200% |
| Simplex (PC) | 64 hrs | 100% | 64 hrs | 0 hrs | Mon 10/9 | Tue 10/31 | 48 hrs | Yes | 244% |
This section is reserved for photographs of the job site at the start of the
project, while in process and upon completion.