Training Room Modification
Best viewed in MS IE 4.0+ at 800x600 Resolution with Java Enabled.


Project Start Date: Fri October 06
Project Finish Date: Tue October 31

This Project was updated on: 09/01/2004 06:35 PM.

PM Home || Project Summary || Current Project Status || Resources || Photos || PM Sample Site

Project Summary

Dates
StartFri 10/06 FinishTue 10/31
Baseline StartMon 10/02 Baseline FinishFri 10/13
Actual StartFri 10/06 Actual FinishTue 10/31
Start Variance 4 days Finish Variance 18 days
Duration
Scheduled18 days Remaining0 days
Baseline 5 days Actual18 days
Variance 13 days % Complete100%
Work
Scheduled162 hrs Remaining0 days
Baseline 168 hrs Actual162 days
Variance -6 hrs % Complete100%
Cost
Scheduled$0.00 Remaining$0.00
Baseline $0.00 Actual$0.00
Variance $0.00 
Task Status
Not Started0
In Progress 0
Completed 45
Total Task45
Resource Status
Resources0
Over Allocated Resources 4
Total Resources 4

PM Home || Project Summary || Current Project Status || Resource || Top || PM Sample Site

Current Project Status

Task IDTask NameStart DateFinish DatePercent Complete
1
Training Room Prep
Fri 10/6Fri 10/6100%
5
Power Modifications
Mon 10/9Thu 10/12100%
22
Network Connections
Mon 10/9Tue 10/10100%
28
Patch Panel Installation
Tue 10/10Fri 10/13100%
34
Testing & Evaluation
Wed 10/11Thu 10/12100%
45
Provide as-built Dwgs
Tue 10/31Tue 10/31100%


PM Home || Project Summary || Current Project Status || Resource || Top || Photos || PM Sample Site

Resources

Resource 
Name
Scheduled
Work
% Work
Complete
Actual
Work
Overtime
Work
Start
Date
Finish
Date
Project
Length
Over
Allocated
Peak
Allocation
DCAA18 hrs100%18 hrs0 hrsFri 10/6Thu 10/1240 hrsYes400%
Double Eagle33 hrs100%33 hrs0 hrsMon 10/9Fri 10/1340 hrsYes150%
SMED (BI)47 hrs100%47 hrs0 hrsMon 10/9Fri 10/1340 hrsYes200%
Simplex (PC)64 hrs100%64 hrs0 hrsMon 10/9Tue 10/3148 hrsYes244%

Photos

This section is reserved for photographs of the job site at the start of the project, while in process and upon completion.